CYCA Redevelopment Update: Week Commencing 28 October 2013

  • Club
  • VIDEO
  • By Jennifer Crooks
  • 28 Oct 2013 17:00:00
SHARE

We are now into the final sprint to the completion of the hardstand. Last week saw the final southern section of the hardstand prepared for the concrete pour that will take place on Tuesday 29 October 2013 as well as concrete being poured for the crane pedestal on the central section.

Additional activities planned for this week include the installation of the following;

  • Jib and YSA Davit Crane
  • Power and water service pedestals
  • Fire hoses
  • Sanivac pumpout system

The plan is for the contractors to vacate the site by Friday 1 November returning full access to the northern car park.

The final detail including the installation of the floating pontoons, ladders, vertical fendering, timber deck extension and wheel stops will commence week beginning 4 November. These activities however will not prevent us from utilising the hardstand.

Howard Piggott
CYCA Commodore

LATEST VIDEOS

  • Rolex Sydney Hobart Yacht Race 2017 - Spirit of Yachting

  • CYCA Trophy Series Day 1 start

  • Video: Blue Water Pointscore Race 5 start - Bird Island

All VIDEOS

LATEST photos

  • Ladies Day Race 1

  • Captain Cook Cruises Top Jocks

  • Blue Water Pointscore Trophy Prize Giving

All PHOTOS